Partial construction of gas block 6 in thermal power plant Brestanica
Scope of work:
- electrical installation works for 110 kV GIS upgrade
- 110 kV cable system and other 110 kV equipment
- assembly, supply and installation of control and protection system
- power transformers supply
Thermal power plant Brestanica decided to invest in two new gas blocks, 6 and 7, which will completely replace gas blocks 1, 2 and 3 from 1974. The new gas blocks will ensure more reliable operation of electroenegetic system of Slovenia for the needs of tertiary regulation, blackstart and power supply for auxiliary system of the nuclear power plant in Krško.
The gas block 6 has been operating since September 2018 and its construction was pre-customized for additional gas block erection. The erection of the gas block 7 began in July 2019. Operation start is was in the beginning of 2021.
Implementation year: 2018
Investor:
- Termoelektrarna Brestanica d.o.o., Cesta prvih borcev 18, 8280 Brestanica, Slovenija